Trafalgar Road
Project Overview
Trafalgar Road was a major arterial reconstruction and widening contract for the Region of Halton completed in 2021. Four Seasons delivered the work as prime contractor.
Trafalgar Road is a principal regional arterial in Halton Region. The contract covered full-depth reconstruction and widening within the contract section, with integrated underground servicing work and full restoration of the corridor on completion.
Four Seasons self-performed the principal trades on the contract. Excavation, granular placement, asphalt paving, and concrete restoration were delivered through in-house crews. Underground servicing including watermain and sewer work was delivered through the dedicated Four Seasons sewer and watermain capability.
Continuous regional traffic, transit operations, and adjacent commercial and residential property access required ongoing staging coordination with the Region of Halton and the local road authority. Book Seven certified traffic control personnel staffed every traffic-affecting work day on the contract.
The contract closed in 2021 within the regional contract administration framework.
Key Aspects of the Work
Regional Arterial Scale
Major arterial reconstruction and widening on one of the principal north-south corridors in Halton Region. Continuous regional traffic, transit operations, and adjacent commercial and residential access maintained throughout construction.
Integrated Underground Scope
Underground servicing including watermain, storm sewer, and sanitary sewer integrated within the road reconstruction scope. Single-prime delivery supported scheduling and coordination across the trades.
Self-Performed Trades
Excavation, sewer and watermain installation, granular placement, asphalt paving, and concrete restoration delivered through Four Seasons in-house crews. Direct accountability across the contract.
Traffic Management
Staging coordinated with the Region of Halton and the local road authority. Book Seven certified traffic control personnel on every traffic-affecting work day. Maintained corridor access throughout construction.
Work Components
| Road Reconstruction | Full-depth pavement reconstruction across the contract limits. Subgrade preparation, granular base placement, and asphalt binder and surface course paving. |
|---|---|
| Widening | Roadway widening to add capacity within the contract section. New travel lanes constructed to the regional design standard. |
| Underground Servicing | Watermain, storm sewer, and sanitary sewer work integrated within the road reconstruction sequence. Service connections coordinated with adjacent property. |
| Concrete Work | Curb and gutter, sidewalks, and structural elements delivered through the Four Seasons concrete crew. |
| Drainage | Storm drainage infrastructure including manholes, catch basins, and pipe installation supporting the reconstructed roadway profile. |
| Restoration | Roadway, sidewalk, and adjacent property restoration completed through the same in-house crews that delivered the underground and reconstruction work. |
| Traffic Staging | Coordinated staging maintained regional traffic, transit operations, and property access throughout the construction period. |